Building service (electrical grid) and industrial structure design at Gaveikiai village, Kamajai eldership, Rokiškis district
May 4, 2020
Building service reconstruction design for 110/10 kV Sendvaris TS, Technikos St. 76A, Klaipėda
May 4, 2020Building service (electrical grid) design for Piktupėnai WT TS (330 kV switchyard), Birštoniškės village, Pagėgiai eldership, Pagėgiai municipality
A new 30/330 kV Piktupėnai WT transformer substation that will support a 300 MW wind farm to a transmission network.

Digital telecommunication infrastructure, planned to be integrated into a LITGRID AB information transfer system.

The switchyard area will include a lighting system, allowing maintenance work even in the dark.